# The 5 Steps to Helical Pier Installation

> Helical piers are so effective at impeding foundation settlement and foundation heave, both of which can be directly attributed to expansive soil.

_Brian Dalinghaus · 2021-04-14_

---

Here at Dalinghaus, we believe helical piers are a heckuva good time, _heliarious_ even.

[[solution:foundation-repair/helical-piers|Helical piers are so effective]] at impeding **foundation settlement** and [**foundation heave**](/blog/what-is-foundation-heave/) (both of which can be directly attributed to **expansive soil** **)** they are now _the industry standard_ for quality **[foundation repair](/foundation-repair/)**.

Helicals differ from push piers and other steel systems in that they have helices (circular sections similar to a staircase or corkscrew) welded to the bottom of the galvanized pipe.

These helicals _anchor_ the structure they are attached to. Imagine your home sitting on underground stilts that are embedded in load-bearing soil or **bedrock**.

**The helicals ensure your home won't go _up_ and won't go _down_, it's locked into place.**

![Galvanized helical pier lead with two helix plates set into an excavated hole beside a house foundation](/assets/blog/steps-helical-pier-installation-2.jpg)

In this article, we are going to cover the 5 main steps of helical pier installation:

- The Inspection
- Prep Work
- Installation
- Lift / Stabilization
- Final Walkthrough

## 1\. The Inspection

The initial step of every foundation repair project is an inspection. A qualified professional locates and diagnoses signs and symptoms of foundation failure
- **[[sign:foundation-repair/leaning-chimneys|Leaning Chimneys]]**
- [**Sloped Floors**](/foundation-repair/soil-stabilization/)
- [**Drywall Cracks**](/blog/reasons-for-sheetrock-cracks/)
- **[[sign:foundation-repair/sticking-doors-windows|Sticky Doors and Windows]]**

A complete and thorough inspection examines the **_interior_** and **_exterior_** of the home, in addition to a thorough analysis of the **_foundation_** itself, whether it be a slab on grade, post-tensioned, or raised.

By the end of the inspection, the homeowner should receive:

- Floor elevation measurements
- And a to-scale CAD drawing of the home

A full set of floor elevation measurements indicate if there is any slope, difference in elevation within the structure of the home (a clear, indicative sign of foundation failure).

Foundation settlement and foundation heave is not necessarily a uniform, across-the-board process. Occasionally, only a particular section of the structure will require attention.

We here at Dalinghuas refer to this section as **_the affected area_** and it's **one of** **the three primary factors of cost**.

We suggest you keep the floor elevation measurements, especially if there are _currently_ no discrepancies in elevation.

These elevations can be used as **a future reference point** if you suspect foundation heave/settlement in the future.

Knowledge is power. Ask for the complete set of floor elevation measurements.

With every measurement in hand, you can see whether the proposed scope of work stays inside the affected area or reaches **_outside_** of it.

Once the inspection is complete and you have your floor elevation plans/CAD Drawing, you will be given a proposal, a rundown of the project's cost.

This is where you'll see if the foundation repair inspector and/or engineer has called for **Helical Piers.**

One of the most common reasons helical piers are implemented is because **you live in a single-story home** and the structure is not inherently heavy enough to drive down push piers.

After the foundation repair contract has been signed, the waiting game begins for the engineering and permitting process.

**Engineering usually takes 3-4 weeks to complete.**

**Permitting can take anywhere between 4-12 weeks depending on the state, county, & city.**

## What Is a Helical Pier?

A Helical Pier is a steel circular/square pipe (utilized in foundation repair) that is hydraulically driven to competent, load-bearing soil and anchored to a structure's prepped footing via a remedial bracket to secure, stabilize and/or lift a structure.

## Helical Piers Are

- Comprised of galvanized steel to impede **rust** or **oxidization**

- Come in sizes ranging from **3′**, **5′**, **7**', **10′** or **20′**

- Comprised of a **lead**, **extensions**, & **remedial bracket**

- Generally pushed down to depths of **25 to 30** feet

Before the Helical Piers can be hydraulically driven into the earth to reach competent, load-bearing-soil, the foundation must be prepped.

Helical piers can be utilized on many different forms of foundation:

- Slab on grade
- Post-tensioned slab
- Raised Foundations

Regardless of the kind of foundation, the Helical Pier locations must be excavated.

Helical Piers are utilized every **6 feet** and their positions are designated via painter's tape so as not to permanently hurt the stucco/siding of the home.

3×3 foot excavations are dug (usually **_18_** **to** **_24_** **inches deep**) at the demarcated locations in order to create access to the foundation's footing.

Occasionally a section of flatwork has to be cut out to reach the footing, and it is repoured once the pier is in.

After the holes are excavated below the footing, the crew utilizes a demo hammer to flatten the footing, preparing it for the remedial bracket which will fit in an **L** shape to the footing.

The remedial bracket is then secured to the footing utilizing one of two methods:

The remedial brackets can be bolted in via "redheads" (bolts with expanding ends that lock into place after implementation) which are hammered in and then secured with a washer and bolt.

**_Titen Screws_**  The remedial bracket can be screwed in with Titen screws that are driven into the footer.

![Titen concrete screw of the kind used to secure a remedial bracket to a footing, on a steel surface](/assets/blog/steps-helical-pier-installation-3.webp)

Both wedge anchors and Titen screws make it **_4 to 5 inches deep_**.

## 3\. Helical Pier Installation

Helical Piers, unlike Push Piers, are not pushed into the earth, they are screwed. The easiest way to remember the differences is **_Push Piers are like nails_** and **_Helical Piers are like screws_**.

The Helical Piers are screwed down to competent, load-bearing soil. Helical piers are implemented through extreme torque via a torque motor which is pinned to a torque bar.

Torque equals the amount of force that is required to rotate the helical into the ground. Intuitively, denser soils require _more_ torque than less dense soil.

Once the load of the home is factored in and we know the amount of helical material that will be implemented, we can calculate for torque to reach the desired loading value.

## Torque Equation Example

(Load Required/K-factor) **x** Drive Head Torque Conversion = Torque Required

Let's put it in numerical values that are similar to your home.

(5,600/8)x 2.5 = 1,750 ft/lbs of torque needed to achieve the required load.

A torque bar is implemented to inhibit the drive head from spinning on the helical pile. The torque bar is attached to the drive head and positioned safely about **5-6** feet away.

If the torque bar is not secured to a stationary object, the torque bar will try to wipe out anything in its path.

The helical piers are then driven into the earth, connected via extensions until competent, load-bearing soil is reached.

## 4\. Lift /Stabilization

After all of the helical piers have been safely installed at each location, the lifting process can begin. The goal of all foundation repair specialists is to achieve **maximum practical recovery.**

Maximum Practical Recovery is the amount of lift that can safely be achieved without compromising the structural (and, occasionally **cosmetic**) integrity of the home.

Not all homes are lifted due to structural and cosmetic concerns; however, homes fitted with helical piers are then considered stabilized as they won't sink any further.

## 5\. Final Walkthrough

Subsequent to the structure's lift and/or stabilization, a final walkthrough takes place. This walkthrough involves a cursory visual of the previously affected areas, with careful attention paid to:

- Previous stucco cracks
- Previous drywall cracks
- Previously sloped floors
- Chimneys (chimneys often have their own, mini foundation)

In addition to visual cues, floor elevation measurements are taken again to compare to the **floor elevations** during the initial foundation inspection.

## Dalinghaus Is Here to Help

If you don't live in our backyard, thanks for reading our **blog**! Check out our article on foundation settlement below

## Schedule a Free Evaluation

Foundation movement is easier to judge in person than from a photo. [Schedule a free evaluation](/contact-us/) and a Dalinghaus specialist will walk the property with you and explain what the evidence shows.