Project Background

The Arris Project Tilt Up is located on one of the many slopes in Diamond Bar that over look the 60 Freeway. Being on a slope and not having an adequate foundation system is place had caused this building to have settled over 8” from it’s time of initial construction. The building is a 2 story tilt up that sits upon a combination foundation consisting of a shallow 36” footing as well as 46 interior and exterior pad footings.

A local investment group had recently purchased the building and has a complete building renovation to ensue after the building’s foundation has been raised and leveled.